The Budget at Completion (BAC) calculator computes the sum of the budget items.
INSTRUCTIONS: Enter the following:
- (PVi) Individual Planned Values. Enter as comma separated values (e.g., 45,10.2,18,79,128)
Budget at Completion (BAC): The calculator returns the Budget at Completion. The calculator also returns useful statistics associated with the individual planned values including;
- (BAC) Budget at Complete
- (n) Number of Values
- (Min) Minimum Value
- (Mean) Average of Values
- (Max) Maximum Value
- (Var) Population Variance
- (SD) Population Standard Deviation
The Math / Science
The Budget at Completion equation is used to compute the sum of all budgets established for the work to be performed. This equation supports the Program Management assessment of project fiscal status using the Earned Value Management approach, which includes this calculation of the Budget at Completion.
The formula for Budget at Completion is:
`BAC = sum_1^n("PV"_i)`
where:
- BAC = Budget at Completion
- PVi = Individual Planned Values
There are multiple PVs for i interim budget values, where this equation offers you twelve input values. The values default to 0.0, and all unused values should be left or set to zero.
For example, if you enter 45,5,6,41,5,66,2 as the Individual Planned Values, you will see:
Results:
(ΣPVi) Budget at Complete : 170.0
(n) Number of Individual Planned Values: 7
(Min)Minimum Value: 2.0
(Mean) Average Value: 24.286
(Max)Maximum Value: 66.0
(Var) Population Variance: 574.776
(SD) Population Standard Deviation: 23.974
- Planned Value is "The Authorized budget assigned to scheduled work." [from PMBoK Guide 5th edition, Glossary]. Planned Value is also referred to as the Budgeted Cost of Work Scheduled (BCWS).
- Cost Performance Index is a measure of the efficiency of expenses expended on a project.
- Estimated At Completion (v1) is the project management metric, the Estimate at Completion (EAC).
- To Complete Performance Index(v1) is: "A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget.” [from the PMBoK Guide 5th edition, Glossary]
- Actual Cost computes the real total cost incurred for the work performed on an activity during a specified period.
- Schedule Performance Index is: "A measure of schedule performance expressed as the ratio of earned value and planned value.” [from the PMBoK Guide 5th edition, Glossary]
- Estimate At Completion (v2) is: "The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.” [from the PMBoK Guide 5th edition, Glossary]
- To Complete Performance Index (v2) is "A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget.” [from the PMBoK Guide 5th edition, Glossary]
- Estimate to Complete computes the expected cost to accomplish all the remaining project work.
- Budget At Completion computes the sum of all budgets established for the work to be performed. This equation supports the Program Management assessment of project fiscal status using the Earned Value Management approach, which includes this calculation of the Budget at Completion.
- Variance at Completion computes the projected amount of budget deficit or surplus in project management assessment.
- Expected Monetary Value is: "A statistical technique that calculates the average outcome when the future includes scenarios that may or may not happen. A common use of this technique is within decision tree analysis.” [from the PMBoK Guide 5th edition, Glossary].
- Earned Value is used to measure the work performed expressed in terms of the authorized budget for that work. [from the PMBoK Guide 5th edition, Glossary]. It is also know as the Budgeted Cost of Work Performed (BCWP).
- Cost Variance computes the difference between earned value(EV) and actual cost (AC). A positive CV is indicative of an under budget while a negative CV is indicative of an over budget.
- Schedule Variance is: "A measure of schedule performance expressed as the difference between the earned value and the planned value.” [from the PMBoK Guide 5th edition, Glossary]
- Present Value computes the present value of money planned or estimated in the future that has been discounted to reflect its current value as if it existed today.
PERT - Program Evaluation and Review Technique
Schedule Float
- Float Start equation computes the slack time available at the beginning of a project schedule.
- Float End equation computes the slack time available at the end of a project schedule.
General Business