The PERT Estimated Average calculator computes the estimated program management value based on the Optimistic Estimate (O), the Most Likely Estimate (M), and the Pessimistic Estimate(P).
INSTRUCTIONS: Enter the following:
- (O) Optimistic Estimate
- (M) Most likely Estimate
- (P) Pessimistic Estimate
PERT Estimated Average (PERTAVE): The calculator returns the weighted average.
PERT (Program Evaluation and Review Technique) Calculators
The Math / Science
This Program Evaluation and Review Technique (PERT) equation computes an estimated average for a set of estimated data. The formula for the PERT Estimated Average is:
PEA = (O + 4 * M + P) / 6
where :
The average is weighted toward the Most Likely value, but takes into consideration both the pessimistic and optimistic estimates.
This estimation equation can be used in Program Management assessment of project goals as defined in the Earned Value Management approach. This technique is often used for estimating project activity durations and resources.
This estimate is derived from three estimates for a value that includes an optimistic value, a pessimistic value and a most likely value [from the PMBoK Guide 5th edition, Glossary]
- Planned Value is "The Authorized budget assigned to scheduled work." [from PMBoK Guide 5th edition, Glossary]. Planned Value is also referred to as the Budgeted Cost of Work Scheduled (BCWS).
- Cost Performance Index is a measure of the efficiency of expenses expended on a project.
- Estimated At Completion (v1) is the project management metric, the Estimate at Completion (EAC).
- To Complete Performance Index(v1) is: "A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget.” [from the PMBoK Guide 5th edition, Glossary]
- Actual Cost computes the real total cost incurred for the work performed on an activity during a specified period.
- Schedule Performance Index is: "A measure of schedule performance expressed as the ratio of earned value and planned value.” [from the PMBoK Guide 5th edition, Glossary]
- Estimate At Completion (v2) is: "The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.” [from the PMBoK Guide 5th edition, Glossary]
- To Complete Performance Index (v2) is "A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget.” [from the PMBoK Guide 5th edition, Glossary]
- Estimate to Complete computes the expected cost to accomplish all the remaining project work.
- Budget At Completion computes the sum of all budgets established for the work to be performed. This equation supports the Program Management assessment of project fiscal status using the Earned Value Management approach, which includes this calculation of the Budget at Completion.
- Variance at Completion computes the projected amount of budget deficit or surplus in project management assessment.
- Expected Monetary Value is: "A statistical technique that calculates the average outcome when the future includes scenarios that may or may not happen. A common use of this technique is within decision tree analysis.” [from the PMBoK Guide 5th edition, Glossary].
- Earned Value is used to measure the work performed expressed in terms of the authorized budget for that work. [from the PMBoK Guide 5th edition, Glossary]. It is also know as the Budgeted Cost of Work Performed (BCWP).
- Cost Variance computes the difference between earned value(EV) and actual cost (AC). A positive CV is indicative of an under budget while a negative CV is indicative of an over budget.
- Schedule Variance is: "A measure of schedule performance expressed as the difference between the earned value and the planned value.” [from the PMBoK Guide 5th edition, Glossary]
- Present Value computes the present value of money planned or estimated in the future that has been discounted to reflect its current value as if it existed today.
PERT - Program Evaluation and Review Technique
Schedule Float
- Float Start equation computes the slack time available at the beginning of a project schedule.
- Float End equation computes the slack time available at the end of a project schedule.